Extensive extension and refurbishment to 1930's detached

Project Overview:

-Client's objective: Maximize plot space to create a large 5-bedroom property.

- Duration: 6 months (including design process and construction).

- Permission: Obtained from Trafford Council after a 3-month design process.

- Services provided: Architectural, engineering, and interior design.

Design and Changes: 

-Original property: A 1930's house with 3 bedrooms and 1 bathroom.

- Transformation: Completely reshaped and taken back to brick.

- Result: Converted into a 5-bedroom property with 3 ensuite bathrooms and 1 additional bathroom.

- Additional features: Spacious kitchen diner, snug cost lounge, front room, sizeable garage, and garden.

Construction Details:

-Demolition: Two sides of the property were demolished.

- Extension: Mini piling was done for the extension, allowing for a steel frame structure.

- Roof: New roof installed as part of the construction process.

Timeline:

- Design and Permission: 3 months.

- Construction (including fitting out): 6 months.

Overall, the project successfully achieved the client's goal of maximizing the plot space to create a spacious 5-bedroom property. The design process and obtaining permission from the council were completed in 3 months, allowing for a head start in the detailed design and procurement phase. The construction, including fitting out, was completed within the following 6 months.